Can I re-plan Production Order Dates when order status is "Planned", after I changed the original Planned Delivery Date on Sales Order ???
Is there chance or I can only achieve this at the PRP phase ?
Thanks for advice

erplncons
17th October 2016, 17:20
The scenario is quite vague.
Is it related to planned production orders or actual production orders? also what planning engine is used (MPS / MRP / SIC / PRP)? what is the time-fence? Do you also have projects (because you have mentioned PRP)

Tomas Toth
18th October 2016, 08:15
Hi
Its related to actual production orders generated thru PRP from the project, that comes from the sales order

erplncons
18th October 2016, 10:32
As per planning engine logic, the planned orders within timefence are not changed. You can get exception messages and accordingly you have to change the orders manually.