stevenlam
11th December 2009, 03:26
AS the attchmented, the order line status is 'to be inspected',the all activities of order is finished.
why not partially of the activities?
PLS give me help,TKS!
DineshSharma
11th December 2009, 07:56
You inspect partly quantity, you received 3 pcs but inspect only one pcs. Please check the warehouse inspection order you get the balance order quantity for inspection.
Regards
Dinesh Sharma
stevenlam
12th December 2009, 02:25
thanks a lot. But all activities of the order are closed...
stevenlam
12th December 2009, 12:04
Dear Joshi,
Thank you for your kindly help. Please note that attachmented.
Thanks!