Hi All,

I am testing a particular scenario in Baan 5.

I what case or scenario can whinp100 have same planned quantities
for a order line of purchase type but in two sequence numbers say 0 and 1.?


Regards,

abby13

nopadon
14th August 2009, 21:33
You can try to do Partial Receipt. then you will see planned inventory transactions by item by next of sequence.

Example . Open Purchase Order , position 10 for 4000 qty.

You can see plan receipt for line 10 sequence 1. after you do confirmed / final receipt for line 10 is 1500 qty.

You will see plan receipt for line 10 sequence 2.

Hopfully , this will answer you question.

Regards
Nopadon