30th June 2009, 07:26
just a questions on baan iv c4 system

I am trying to copy PO's from existing po created e.g.
po no: 880001
to 88 (880002)

the reason is in 880001 has 50 lines and text details and currency with EUR.

Now i want to copy all the lines with text details but want to change the currency to USD.

this will save time to re enter the all the lines and text to new po 880002.

IS THERE ANY OPTIONS TO CHANGE THE CURRENCY WHILE COPYING TO NEW PO OR AFTER COPYING THE PO.

Please advice

thanks in advance.

sushil
1st July 2009, 06:50
try this.

1.Create Purchase order header in session tdpur4101m000 with currency USD in form 2 & save it, (lets say PO - B) no need to maintain lines.
2.Open the PO - (that needs to be copied, PO-A) which has EUR currency
3.Click on Copy button - enter the source PO as A , target as B .
4.click on continue.

hope this helps.

baan999
2nd July 2009, 07:08
Thanks ... It is working fine....