GaryEd
27th April 2009, 18:32
My understanding is that the company calendar is only used for production planning and that purchasing uses a default 5 day work week.
First off, is that correct?
Secondly if so, is there any way to prevent MRP planning purchase order deliveries for certain dates? We have shut down weeks where the company is closed and would like to prevent MRP planning for deliveries during those periods.