17th April 2007, 08:14
dear all,
Please help me or this situation.
I have 2 (two) warehouses. One of that warehouse is nettable type and the another is non nettable warehouse.
I have scenario like this if inventory in nettable minimum 6 kg (weight from 1 cartoon) then make RPL to nettable warehouse.
Can this scenario otomatic so I don't need to input RPL manually.
Please advice.
Rgds,
Robby
sukesh75
17th April 2007, 12:29
Hi Robby,
I doubt if you could do this automation in Baan4. Probably you would have to do it with the help of AFS...
sk
Paul P
18th April 2007, 06:20
Step 1: Make an AFS-powered session that checks inventory and, if inventory level exceed certain threshold in source warehouse, perform all RPL steps automatically for you
Step 2: Put this AFS-powered session in a job and have it run regularly as you see fit
Rgds,
Paul
abas_cool
19th April 2007, 03:49
sorry I want ask about AFS.
what it is ?
how I can find it ?
thank you.
rgds,
Robby
filipd
23rd April 2007, 14:39
Since you have a nettable and a non-netaalbe warehouse, I would suggest to use DRP (distribution requirements planning). You could compare this with MRP, but instead of making planned production/purchase orders, DRP generates planned replenishment orders from the nettable to the non-nettable warehouse as soon as the inventory drops below a certain level.
Maybe you could ask your account manager or look at the Infor site for documentation about DRP.
george7a
23rd April 2007, 14:44
sorry I want ask about AFS.
what it is ?
how I can find it ?
thank you.
rgds,
Robby
Hi Robby,
Please read this the following link & the documents attached to it:
http://www.baanboard.com/baanboard/showthread.php?t=7251
- George
Hutje33
24th April 2007, 13:03
funny how fast the "techies" amongst the board members stand up with their technical solutions. but sometimes Baan has standard options which work pretty nice, like in this case drp........:rolleyes: