rkathait
4th November 2006, 00:38
Can anyone confirm if Generate Order Advice session generates order advice based on working days or calendar days? I'm getting very weird results and seems that if the lead time in Item-supplier data is 1 or more than it considers working days and if the lead time is 0 then it considers calendar days.
Thanks & regards

frankadam
10th November 2006, 02:04
Hi,

Yes, the calendar is used. You might want to check the blank availability type set up for the calendar. It's generally recommended to set that to 00:00 - 24:00. If you have it set up as for example 8 hour days, then a lead time of 1 day will effectively be 3 days.

I hope this helps,
Frank

rkathait
10th November 2006, 02:32
Thanks Frank,

I did log an inquiry for this and Infor is looking into this. I'm being told that it does not consider the calendar and hence it is just the calendar days.

Also the blank availablility type is set for 24hrs, so this shouldn't be a issue. I'll post the reply from Infor in this thread...